The construction team at Beverly Grant is hard at work on the new shelter. Within the next week they anticipate finishing the soil nail walls and pouring more concrete into the deep foundation. This is a big milestone in the project and means we are getting closer to vertical construction, which is projected for late July. Already, a driveway has been cut in, stormwater retention systems have begun to be installed, sewer lines have been laid and the parking area retaining walls have been built. The construction team recently increased the size of the water lines to ensure adequate flow for the new sprinkler system. Construction is predicted to be finished by June 2026.