Helpmate Hotline: (828) 254-0516 | Business Line: (828) 254-2968

August 5, 2026

Thanks to the team at Beverly-Grant, construction at Joy’s House continues to move forward, and exciting progress is happening both inside and outside the building.

Inside, the first coat of paint has now been completed throughout the building, with the fitness room being the only space still awaiting its first coat. The bathrooms are also taking shape, with all tile installation now complete. In the kitchen, range hoods have been installed, bringing the commercial kitchen one step closer to completion. Flooring installation will begin soon throughout the remainder of the building, adding another major finishing touch.

Outside, crews are actively installing the roof, with gutters scheduled to be installed next week once roofing is complete. The smoker’s canopy is also nearing completion, adding another important outdoor feature to the campus.

Utility work continues to make steady progress as well. Joy’s House now has temporary permanent power, and crews are preparing to tie the building’s water service into the main line.

Every week brings Joy’s House one step closer to opening its doors and providing survivors and their children with a safe place to rebuild their lives. 

February 5, 2026

The team at Beverly-Grant continues to make steady progress, with several major building systems now in place and others moving toward completion.

Work is underway to install insulation over the stair towers, which is an important step before the siding can be added. Windows are nearly finished throughout the building, and crews have begun sealing them to protect against weather. The remaining windows in the stairwells will be installed last, which is typical for this stage of construction.

Inside the residential portion of the building, all plumbing waste piping has been installed, inspected, and approved. Installation of copper water lines is now in progress, which will supply water to the apartments. Heating and cooling work is also moving forward, with HVAC venting and ductwork currently being installed.

The central staircases are fully complete, providing permanent access throughout the building. On the exterior, installation of fascia and soffit (the finished edges and undersides of the roofline) is underway, giving the building a more complete appearance. Spray foam insulation has been installed along the building perimeter and throughout the first- and second-floor residential corridors, and this work has passed inspection.

December 12, 2025

The team at Beverly-Grant continues to make huge progress on the shelter. Inside, the plumbing is moving forward with the rough-in work, and the electricians are laying out where outlets, switches, and fixtures will go and drilling the pathways needed for wiring.

On the exterior, the crew is working on the roof structure. They’re installing the sub-fascia and adding the sheathing to the trusses, which helps tie the roof system together and prepares it for the next phases of construction. Once this work is complete, the team will begin building the interior stairways.

November 24, 2025

The team at Beverly-Grant has made a lot of exciting progress recently. The structural framing for the residential side of the building is now complete, and crews have begun putting up the interior walls that divide the individual units. Work on the exterior sheathing is also underway — this is an important step that helps protect the building from the elements as we move toward “drying in,” or sealing the structure from weather. Plumbing rough-in began on 11/12, and we expect windows to arrive within the next week to week and a half. Once they’re here, the team will wrap the openings and install the windows so the building can be fully closed in. Electrical rough-in is scheduled to start in the second week of December, depending on how quickly the building is dried in.

November 3, 2025

Exciting progress continues at the future site of Joy’s House! Recent work has focused on completing foundational preparations and beginning the structural framing of the building.

Crews have finished the underground plumbing and electrical work and installed the natural gas line that will connect to the building’s generator. After carefully marking the foundation and setting the base supports, framing began in earnest.

The residential portion of the building is now coming to life—framing and flooring for both the first and second levels are complete. The office area has also reached the same milestone, with its framing, floor trusses, and sheathing finished.

Each step brings us closer to opening the doors of Joy’s House, a safe, welcoming space that will double our shelter capacity and provide comfort and dignity to survivors of domestic violence in our community.

Stay tuned for more updates as construction continues!