The team at Beverly-Grant continues to make huge progress on the shelter. Inside, the plumbing is moving forward with the rough-in work, and the electricians are laying out where outlets, switches, and fixtures will go and drilling the pathways needed for wiring.

On the exterior, the crew is working on the roof structure. They’re installing the sub-fascia and adding the sheathing to the trusses, which helps tie the roof system together and prepares it for the next phases of construction. Once this work is complete, the team will begin building the interior stairways.