The team at Beverly-Grant continues to make steady progress, with several major building systems now in place and others moving toward completion.
Work is underway to install insulation over the stair towers, which is an important step before the siding can be added. Windows are nearly finished throughout the building, and crews have begun sealing them to protect against weather. The remaining windows in the stairwells will be installed last, which is typical for this stage of construction.
Inside the residential portion of the building, all plumbing waste piping has been installed, inspected, and approved. Installation of copper water lines is now in progress, which will supply water to the apartments. Heating and cooling work is also moving forward, with HVAC venting and ductwork currently being installed.
The central staircases are fully complete, providing permanent access throughout the building. On the exterior, installation of fascia and soffit (the finished edges and undersides of the roofline) is underway, giving the building a more complete appearance. Spray foam insulation has been installed along the building perimeter and throughout the first- and second-floor residential corridors, and this work has passed inspection.