The team at Beverly-Grant has made a lot of exciting progress recently. The structural framing for the residential side of the building is now complete, and crews have begun putting up the interior walls that divide the individual units. Work on the exterior sheathing is also underway — this is an important step that helps protect the building from the elements as we move toward “drying in,” or sealing the structure from weather. Plumbing rough-in began on 11/12, and we expect windows to arrive within the next week to week and a half. Once they’re here, the team will wrap the openings and install the windows so the building can be fully closed in. Electrical rough-in is scheduled to start in the second week of December, depending on how quickly the building is dried in.